I want to remove about 1 cubic meter of concrete myself. What are my options?
Teilen
-
Chiseling with a hammer drill
-
You may have one at home or can borrow one.
-
Estimated duration: about 1 to 2 working days
-
Costs: very low, some wear and tear, and my own labor (free?)
-
I rent an excavator with a hydraulic breaker
-
Can I operate an excavator myself?
-
Is the work site accessible with it?
-
Duration: about 2 to 3 working hours
-
Costs: about 350 euros, perhaps more with delivery and collection
-
I blast the concrete block with BETONAMIT®
-
I drill holes approx. 30 mm into the concrete
-
I mix 5kg of BETONAMIT® powder with 1 liter of water
-
I pour the mixture into the holes
-
I wait; the next day I can easily remove the resulting parts
-
Duration: around 3 hours to drill and fill the holes
-
Costs: 60 - 120 euros for Betonamit
-
Conclusion: In terms of cost-benefit analysis, BETONAMIT® comes out on top!