As a company, I have been tasked with removing 1 cubic meter of concrete for a client. What are the available options?
Teilen
-
Chiseling with a rotary hammer
-
This is certainly available.
-
Estimated duration about 1 to 2 working days with one man
-
Costs, very high, because many man-hours are incurred, around €1000 - 1500
-
With an excavator with a hydraulic breaker
-
Do I have the excavator myself?
-
Can I operate an excavator myself or do I need an operator?
-
Is the work site accessible with it?
-
Duration about 2 to 3 working hours
-
Costs about 350 euros, perhaps more including transport to and from the site, naturally less if the excavator is already available
-
We blast the concrete block with BETONAMIT®
-
We drill holes of about 30 mm into the concrete
-
We mix 5kg of BETONAMIT® with 1 liter of water
-
We pour the mixture into the holes
-
We call it a day, the next day we can simply remove the resulting pieces
-
Duration, around 3 h of drilling and filling the holes
-
Costs 60 - 120 euros for BETONAMIT®
-
Conclusion: Using BETONAMIT® in this example can yield the most profit with little effort.